Complementary Work for Network Rehabilitation of As-Salt Downtown (Naqab Swada)

The Works involve the supply and installation of primary system, tertiary network reinforcement, installation of house connections and the testing - possibly including the repair or replacement - of water pipeline already installed; within the City of As-Salt.
     Water primary distribution pipelines DN150 to DN200, length approx. 1.3 km
     Water tertiary network PE63 and PE125 length approx. 11.0 km
     Approx. 2,900 house connections; and pressure testing, flushing and sterilizing of approx. 47 km of PE63, PE125 and DN150 pipelines already laid, including possibly the repair or replacement of some pipeline
 

employer
Ministry of Water & Irrigation
consultant
Dorsch Gruppe
sector
Under Construction
Location
jordan /Salt
completion date
28/05/2023