The Works involve the supply and installation of primary system, tertiary network reinforcement, installation of house connections and the testing - possibly including the repair or replacement - of water pipeline already installed; within the City of As-Salt.
Water primary distribution pipelines DN150 to DN200, length approx. 1.3 km
Water tertiary network PE63 and PE125 length approx. 11.0 km
Approx. 2,900 house connections; and pressure testing, flushing and sterilizing of approx. 47 km of PE63, PE125 and DN150 pipelines already laid, including possibly the repair or replacement of some pipeline