APC NEW RED POTASH WAREHOUSE IN AQABA - PKI - UN LOADING STATION

Project Description:

The Work of the Project is defined by the Contract Documents and consists of the following:
a) The dismantling of the existing water tanks and handing over all parts to the Employer
b) The demolition of the existing water tanks foundations and clearing the area for new construction
c) The construction of new water tanks and related utilities as per tender documents and drawings
d) The relocation of the existing water pumps and all related accessories to the new tanks’ locations
e) The demolition of cxisting facilitics to clear the area for the new unloading station construction as per relevant documents and drawings
f) The survey and relocation/constructing new replacement of existing utilities that may be affected by the new constructions
g) The safe modification and reinforcement as applicable of the existing conveyors (S5, S6 and S7) tunnel as per relevant structural requierments documents, drawings and details
h) The modifications of the existing conveyors S5, S6, and S7 to accommodate new material loading points including without being limited to all equipment parts, idlers, new skirting, dust extraction modifications, and any required modification for the well and safe operation of the equipment to the Employer’s satisfaction
i) All related utilities, connections, pipes, chutes and duct works
j) All related HVAC and Drainage works k) All related civil, structural, electrical, and instrumentation and control works
 

employer
Arab Potash Co.
consultant
Arab ALhandseh
sector
Industrial
Location
jordan /Aqaba
completion date
30/11/2022