Restructuring & Rehabilitation of DZ-04, DZ-05, DZ-18, Water Supply Network

Description of the similarity in accordance with Criterion 4.1 (h) of ITT 1 - Instruction to Tenders.

The project implemented in water sector and analysis for water system.    The project implemented in water sector and analysis for water system.

Scope of Work:
Supply, install and Commissioning and decommissioning of water pipelines including all fittings, Valves, PRV`s, meters, and accessories in order to restructuring of Um Shujairat (DZ 18) AlTaj & Al Jufeh (04&05) distribution zone of the Greater Amman Water
The distribution zones were hydraulically analyzed, some DMAs were split, some borders were shifted and main feeders for the DMAs were proposed.

The Project Includes the following: 
-    Supply, install and commission and decommissioning of water pipelines including all fittings, valves, PRVs, meters and accessories.
-    Construct new chambers for the PRV.
-    Supply, install and commission electrical floaters to detect if there is a flood in the chamber. 
-    Designing and install the solution of main power supply which is required for operating all the instruments under this contract such as valves, PRVs. Meters. 
-    Supply and install house connections to any replaced pipeline and/or reconnecting existing house connections to the replaced pipelines.

The project conducting hydraulic modeling
•    The Project Include: Conducting water Pipeline with Verification of the Hydraulic Profile for the Pipeline Network. 
•    Hydraulic Modeling was represented in zones distribution, as some DMAs were split, some borders were shifted and main feeders. 

The project included laying pipes and valves installation
•    The Project Include: Supply, install and Commissioning and decommissioning of water pipelines including all fittings, Valves, PRV`s, meters, and accessories. 

•    Pipe Laying Quantities: 
-    DI Pipes with DN 100 to 600 mm with total length of 23 km. 
-    HDPE Pipes with DN 50 to 150 with a total Length of 6.2 km. 

Installing pumps, pump stations. 
•    The Project Include: Supply, install, test, Commission & Operate two Horizontal end Suction pumps. 
-    Pumps Duty Point (500 m3 / hr. 36m. )
 

 

employer
Jordan Water Company (Miyahuna)
consultant
Arab Dar Engineering Co.
sector
Water Projects
Location
jordan /amman
completion date
01/01/2023