Contract 6: Construction of Basateen Pump Station and Reservoir - Zarqa

 1. The overall scope of work of THIS Contract 6 comprises the following:

2. Construction of pumps room (Consist of four centrifugal pumps with 104 L/sec capacity and 185 m head & submersible drain pump with a duty flow of 7 m3/h at 7m head and one water booster pump) .

3.   2. Construction of on-ground reservoir of 2000 cubic meters capacity. The reservoir will be separated into two compartments. The nominal dimensions of the reservoir are 12.7 m X 20.9 m.

4.   3. Construction of yard piping, valve and metering vaults, connections to existing piping, site and main entrance improvements, fencing, pavement, and landscaping.

5.   4. Procurement, installation, testing, startup, and commissioning of equipment and systems including: pumps and motors; surge tanks; piping; valves; chlorination equipment; hoisting cranes; heating, ventilation and air conditioning; electrical; and instrumentation and controls.

6.   5. Coordination and cooperation with all other contracts and contractors to ensure proper and seamless commissioning and transitioning.

employer
Water Authority of Jordan
consultant
HAZEN AND SAWYER P.C., in Joint Venture with DAR AL- OMRAN Infrastructure and Environment
sector
Water Projects
Location
jordan /Zarqa
completion date
15/06/2014