Extension & Rehabilitation of Wastewater Collection System in Mafraq City

The scope of work comprises the supply, construction, installation, and testing of sewerage facilities in the area of Mafraq. The works shall incorporate, but not necessarily be limited to supply of all materials and install the following elements:
• Corrugated Polyethylene sewer pipelines DN200 to DN400, length approx. 43 km;
• Reinforced concrete sewer pipelines DN 500 to DN 900 approximately 7.5 km
• Inspection and connection Manholes of precast elements and ductile iron heavy duty covers 1,900 number;
• Pump Station for Q= 33l/s and H=35m with 2,550 m HDPE force pipeline.
• Approx. 3,000 house connections with revision manholes and Polyethylene pipelines DN150;
• Replacement of about 11 km pipelines of the existing collectors.

employer
Water Authority of Jordan
consultant
c/o Dorsch International Consultants GmbH
sector
Water Projects
Location
jordan /Mafraq
completion date
31/03/2019