Five Pilot Projects have been. Selected for the installation of a first set of Energy Saving measures, and to be a project for the relevant Ministries to promote the EEPB project and test different technologies:
• AI Nadeem hospital in Madaba - MoH
• AI Basheer Hospital - Obstetrics building - MoH
• Amman Comprehensive Health Center - MoH
• Thoqan Hindawy school for boys - MoE
• MoPWH building – MoPWH
The PROJECT includes the following energy saving measures:
1. Lighting - lamp and fixture replacement
2. VRF (MoPWH only)
3. Photo Voltaic
4. Heating System Improvement - Distribution System Insulation, Maintenance, Boiler Calibration, Thermostatic valves.
5. AJC Split Unit replacement to inverter type
6. DHW Solar Thermal collectors
7. Energy Monitoring System
PHOTO VOLTAIC SYSTEM SCOPE:
Design and construction of a photo voltaic system with a total capacity of 795 KWP including all related civil, steel and electrical works for the above mentioned buildings, of which 500 KWP as car parking in Ministry of Publics works and Houses